Milestone note Oct 1, 2026

TVA got the first US construction permit for a commercial SMR — in 14 months, four ahead of schedule

The NRC issued the Tennessee Valley Authority a construction permit for a 300 MW GE Vernova Hitachi BWRX-300 at Clinch River, Tennessee, at the end of September — the first US construction authorisation for a commercial small modular reactor. The review took 14 months from the April 2025 application, about four months faster than the NRC's own schedule. It is permission to build, not to operate.

Milestone note Sep 28, 2026

First US construction permit for a commercial small modular reactor

Reached

TVA / GE Vernova Hitachi BWRX-300 — Clinch River, Tennessee — The NRC issued the Tennessee Valley Authority a construction permit for a 300 MW BWRX-300 at its Clinch River site in Oak Ridge at the end of September 2026 — the first US construction authorisation for a commercial small modular reactor, and the first held by a utility rather than a reactor developer. The review took 14 months from TVA's April 2025 application, about four months ahead of the NRC's own schedule. A construction permit is not an operating licence: TVA must build the plant and obtain a separate licence before loading fuel. TVA has said the site could host up to four units; the design's first unit anywhere is Ontario Power Generation's Darlington project, targeted for 2030.