Washington lined up equity stakes in two fusion companies — paid for in chips, not reactors

The Commerce Department signed CHIPS letters of intent on October 22 for up to $389M across four companies, including up to $175M for Helion and $85M for Commonwealth Fusion Systems, with a minority, non-voting federal equity stake as a condition. The money is for power and radiation-hardened semiconductors fusion plants need. These are letters of intent, not final awards.

Milestone note Oct 1, 2026

Helion quietly rewrote its 2028 promise: Orion will 'begin initial operations', not make electricity

Helion changed its website from saying Orion, the fusion plant contracted to supply Microsoft, would produce electricity by 2028 to saying it will "begin initial operations in 2028". A spokesperson said the plant would "in no universe" reach its full 50 MW in 2028, putting full power in 2029 or 2030, and the goal for the Polaris prototype changed from net electricity to demonstrating electricity from fusion.

Milestone note Jun 2026

World's first regulatory licenses for a fusion power plant

Reached

Helion Energy / Washington DOH — Helion secured the licenses to build and operate its Orion plant in Malaga, WA — a Radioactive Materials License and a Radioactive Air Emissions License from the Washington Department of Health — the first US (and world) fusion firm to clear full plant licensing. Under the NRC's decision to regulate fusion like particle accelerators rather than fission reactors, the state DOH is the licensing body. Electricity to Microsoft is targeted by 2028. In September 2026 Helion softened that: its website now says Orion will "begin initial operations in 2028" rather than produce electricity then, a spokesperson said the plant would "in no universe" reach its full 50 MW in 2028, putting full power in 2029 or 2030, and the stated goal for its Polaris prototype changed from producing net electricity to demonstrating electricity from fusion. The Microsoft contract requires Orion to be connected to the grid and begin operations by the end of 2028.